15/06/2008 by Martin Sargent.
We have now started to lay the blocks for the first villa and it is starting to take shape.
This is the view from the back of the villa where you can see the shapes of the rooms.
Posted in Current construction projects, Client - Hitesh | Print | No Comments »
07/06/2008 by Martin Sargent.
Natura design. Lanzarote builders of Luxury villas and custom built swimming pools.
The floors are being laid for the second villa’s basement and the water tanks are now finished.
![]()
This is the technical control checking the steel work for the roof and also taking samples of the concrete which they take back to the lab to check the quality. They follow the build from start to finish making sure the project is built exactly according to the plans and the quality of the materials used are of European standard for the seguro decenal.
The roof of the basement is finished and ready for pouring the concrete. The man below is controlling the flow speed of the concrete by remote control and is being directed by the builder who is pouring the roof.
The roof has taken 50 cubic metres of concrete to cover and will only take a few hours to go off.
The first blocks are being laid for the first floor of the villa.
Posted in Current construction projects, Client - Hitesh | Print | No Comments »
01/06/2008 by Martin Sargent.
The acro props have been put into position to support the main structure of the ceiling of the basement.
All the ceiling blocks are in place. We will finish the final steel work on Monday morning ready for pouring the concrete for the roof. This will be the first stage of the major construction work completed.
Posted in Current construction projects, Client - Hitesh | Print | No Comments »