Lanzarote builders Playa Blanca Update

Today we are pouring the final concrete for the completion of the basement walls for the second villa. We will also pour all the supporting columns for the first storey. The technical control and quality control technicians visited the site this morning and gave us the ok to pour the concrete.

Natura Design Lanzarote Builders Pouring the concrete

We have started to backfill the supporting walls. These were first damp-proofed with pitch paint and a special plastic membrane to keep out the water.

Martin Shuttering Concrete lorry

The majority of work is now completed on both of these basements. All the shuttering and cardboard columns have been removed and the concrete floor had been laid. We are now preparing the ramp down to the underground car park.

Natura Design Lanzarote builders The wall are finished Floor is laid

I am pleased with our progress so far, everything has gone smoothly and we are on schedule.

Lanzarote Builders.