29/11/2007 by Martin Sargent.
The swimming pool has been topped up, the fountain works very well and all the pool lights are now working.
I have moved the Heat pump and we are running the final checks for everything.
Posted in Pools - Heating, Pools - Finished, Pools - Under Construction, Client - Ron | 1 Comment »
17/11/2007 by Martin Sargent.
The pool is now finished and we are starting to fill it with water. The filter has been filled with sand and we have plumbed in the heat pump leaving plenty of long lengths of tubing for the future instillation of a salt chlorinator. The electrician will finish off on Monday morning and i am getting him to put the light switch in the sitting room, to turn on the new outside lights, that the ones next to the BBQ, the spots and the lower wall lighting, there is room for one more switch next to the existing one.
Posted in Pools - Under Construction, Client - Ron | No Comments »
13/11/2007 by Martin Sargent.
The glassing is now finished.
We will tile the pool edge tomorrow and I will start to fill the swimming pool with water this weekend I will also Install the heat pump.
The ramp to the garage is also finished.
The non slip is on all steps and swimming pool surround.
Posted in Pools - Under Construction, Client - Ron | No Comments »
07/11/2007 by Martin Sargent.
The first coat of resin has been rollered on the swimming pool
We are about to concrete the driveway entrance
Posted in Client - Ron | No Comments »